Building health · MANHATTAN, NY
built 1950 · 6 stories · 55 apartments
The building’s record over time
Filings, permits, complaints and violations from city records, newest first. Highlighted rows are unresolved and from the last year; older unresolved records are marked “never closed”. Tap any row to read it on the agency’s own site.
2026 May
1 active elevator; latest periodic inspection May 2026
DOB NOW Elevator Safety Compliance
2026 Apr
Latest accepted inspection Apr 2026, defects reported: no
DOB NOW: Safety Boiler
2026 Jan
Boiler burning No. 2 oil (Federal FST-100), registration current since Jan 2026
Clean Air Tracking System (boiler registrations)
2025 Oct
VT-PER-CO Elevators
DOB Violations
2025 Oct
Plumbing permit
DOB NOW: Build – Approved Permits
2025 Apr
General construction permit
2025 Apr
General construction permit
2024 Feb
Safe with a repair and maintenance program (cycle 9, filed Feb 2024)
DOB NOW: Safety – Facades Compliance Filings
2023 Nov
BE-EXT-LP Boiler
DOB Violations
2023 Nov
BE-EXT-LP Boiler
2019 Aug
Outside FEMA's 1% annual-chance flood zone: X
FEMA National Flood Hazard Layer
2019 Feb
General construction permit
DOB NOW: Build – Approved Permits
2018 Jul
Plumbing permit, General construction permit
2013 Feb
No active shed permit
2011 Nov
Plumbing permit, General construction permit
2011 Jul
General construction permit
2011 Jul
Plumbing permit
1989 May
Smoke or CO detectors class A · never closed
Housing Maintenance Code Violations
1989 May
Fire safetyApt 3E class B · never closed
1989 May
Fire safety class B · never closed
1988 Aug
Electrical class B · never closed
1950
Built
PLUTO (tax lot data)
Dates are the city's record dates, shown to the month.
These are city records, not an inspection by Blueflo. Every item shows its source and the date it was last checked.